WEBVTT

00:00:00.600 --> 00:00:03.966
Want to know if your project will have enough cash?

00:00:03.966 --> 00:00:10.631
Here is how to record your budget, contracts and payments in Propool, and see your cash week by week.

00:00:11.931 --> 00:00:17.179
Your project's Overview shows what buyers have paid, and what's due next.

00:00:17.179 --> 00:00:23.865
To plan your cash, go to Project costs and cash planning, and choose Review cash assumptions.

00:00:23.865 --> 00:00:32.996
Enter the cash you have now, how much of each installment you expect to collect on time, and where your cash figure comes from.

00:00:32.996 --> 00:00:36.590
Add a reason, then choose Review cash assumptions.

00:00:36.590 --> 00:00:41.838
Propool now projects your cash week by week, for the next thirteen weeks.

00:00:43.138 --> 00:00:45.675
Next, choose Add cost record.

00:00:45.675 --> 00:00:52.235
Choose Original budget, then add a cost code, a description and the amount.

00:00:52.235 --> 00:00:57.221
Add the source and a reason, then choose Add cost record.

00:00:57.221 --> 00:01:01.157
Your budget now shows as the Approved budget.

00:01:02.457 --> 00:01:08.681
When you sign a contract, add it as a Commitment, with its amount and the date it's due.

00:01:08.681 --> 00:01:13.349
Add the contract number and a reason, then choose Add cost record.

00:01:13.349 --> 00:01:17.875
The contract now shows as an expected cost in the week it's due.

00:01:19.175 --> 00:01:24.157
When you pay, add a Paid actual, and match it to the contract.

00:01:24.157 --> 00:01:29.380
Add the bank reference and a reason, then choose Add cost record.

00:01:29.380 --> 00:01:36.451
Paid to date goes up, and only the unpaid part of the contract is left in your forecast.

00:01:37.751 --> 00:01:44.461
Your cash has changed, so Propool asks you to review it: choose Review cash assumptions.

00:01:44.461 --> 00:01:49.418
Enter your new balance and where it comes from, and add a reason.

00:01:49.418 --> 00:01:52.163
Then choose Review cash assumptions.

00:01:52.163 --> 00:01:57.348
The reminder is gone, and the forecast starts from your new balance.

00:01:58.648 --> 00:02:08.540
Every budget, contract and payment is listed under Cost records, and Correct entry fixes a mistake while keeping the original.